\n \n Salon Equipment Order Timeline: Deposit to Opening | Nova

Salon Equipment Order Timeline: From Deposit to Opening Day

I’ve seen a beautiful new salon open two weeks late because the beds were still on a ship. I’ve also seen a space sit finished and empty for a month because the owner ordered in the wrong sequence: reception desk first, treatment beds last. Neither problem was a supplier issue. Both were calendar issues.

Buying salon equipment is a construction project with a shipping lane attached. If you’re opening or expanding a location in the US, the order timing matters as much as the spec sheet. Here’s the sequence that keeps an opening on schedule, based on what actual lead times look like right now.

The Real Lead Times, Item by Item

Before you build a calendar, you need honest numbers. These are the ranges I’d plan with for imported equipment in 2026:

ItemProductionSea freight to USTypical order point
Electric treatment beds10-15 days4-6 weeks14-16 weeks out
Shampoo beds and backwash units10-15 days4-6 weeks14-16 weeks out
Reception desks (custom)15-20 days4-6 weeks16-18 weeks out
Manicure tables and trolleys10-15 days4-6 weeks12-14 weeks out
Styling chairs, stools10-15 days4-6 weeks12 weeks out

Add two things to every row: customs clearance, which usually takes three to seven days, and one buffer week. A 4-6 week ocean transit can become seven weeks if the vessel gets rolled or a port gets congested. If your lease starts on March 1, the deposit needs to leave in November, not January.

Week-by-Week: A 16-Week Plan

Weeks 16-14: Lock the layout, then order the big pieces

Beds, shampoo units and custom reception desks go first because they’re the longest lead and the hardest to change later. Confirm room dimensions, door widths and elevator size before the deposit. A queen-size bed frame that won’t fit in a 32-inch stairwell is a very expensive mistake, and it’s the kind of thing delivery day planning should catch early, not on the sidewalk.

This is also the week to check the floor. A treatment bed with a client on it concentrates load in four small points. Tile over a wood subfloor can crack; a 100-year-old building may need a simple span check. This floor load guide explains what to ask a contractor.

Weeks 13-10: Order everything that isn’t bolted down

Trolleys, manicure tables, stools, lamps, towel warmers. Smaller items can arrive later and be stored more easily, but they still come on the same ocean schedule. Ordering them with the beds usually saves freight and lets you consolidate one delivery instead of four.

Weeks 10-6: Build-out and pre-delivery checks

This is when the room gets its plumbing, electrical and flooring. It’s also when you confirm power. Our electric beds run on 110V-240V dual voltage and are CE certified, so they don’t need a transformer in a US suite, but each unit still needs a dedicated circuit within reach of the motor cable. If your electrician is installing outlets in week six, you’re on time. If you’re asking in week two, you’ll be running extension cords behind a bed.

Get the certificate of insurance and delivery paperwork to your landlord now. Loading dock reservations, freight elevator bookings and building access hours are all things that get denied at the last minute.

Weeks 6-2: Freight, customs and receiving

With DDP door-to-door shipping, the freight, duties and customs clearance are handled for you, and the container arrives at your address rather than a port. You still need to be ready: a liftgate for a residential or small commercial address, a clear path to the door, and two people who can help move crates. Inspect the crates before signing. Photograph any crush damage and note it on the delivery receipt — that single habit is what makes a damage claim possible.

Weeks 2-1: Assembly, punch list, staff training

Beds and desks assemble in a few hours each with basic tools. Leave a full week for it anyway, because something always needs a missing bolt or a second pair of hands. Train your team on the motors and remotes before opening day so nobody discovers a stuck foot pedal with a client in the chair. Every unit ships with a one-year warranty, and the first week is the right time to log any issue while it’s clearly a transit or factory problem.

What to Buy Locally Instead

Not everything should cross an ocean. Linens, consumables, small tools, cleaning chemicals and anything you might need to replace in a week are better bought from a US distributor. Import the structure — beds, desks, tables, shampoo units — and buy the soft goods locally. That split keeps your capital in the items that last a decade and your cash flow flexible for the things that don’t.

Budgeting the Freight and the Buffer

DDP pricing means the number you’re quoted includes shipping and duties, which makes comparison shopping much easier. Budget another 5% to 8% of the equipment total for the surprises: a liftgate fee, a storage month if your build-out slips, an extra electrician visit. And budget time the same way. A two-week buffer at the end of the schedule is not padding — it’s the difference between opening calm and opening with a clipboard in your hand.

If you’re outfitting more than one room, our salon and spa equipment range covers beds, backwash units, desks and storage from one factory, with MOQ 1 so you can order a single sample before committing to a full build. Production takes 10-15 days, DDP delivery to the US runs about 4-6 weeks, and you can stage the order in phases if your build-out is still in permits.

FAQ

How far in advance should I order salon equipment before opening?

Plan on 14 to 16 weeks for beds and custom desks, and 12 weeks for smaller items. That covers 10-15 days of production, 4-6 weeks of ocean freight, customs clearance and a buffer week for delays.

Can I order equipment before my build-out is finished?

Yes, and most owners do. Just confirm storage: a climate-controlled unit costs roughly $150 to $400 a month depending on size, and vinyl or wood finishes shouldn’t sit in an unheated garage through a cold snap.

What happens if my equipment arrives damaged?

Inspect the crates before you sign the delivery receipt, photograph any damage and note it in writing. Then contact your supplier with the photos and the order number within 48 hours so the claim can be filed while the shipment record is still fresh.

Shopping Cart